I've noticed / read referrals to concrete being poured over 2+ times getting 'bonded' but I can't find any information to what the longest you can wait is certainly.
What is usually the longest you can wait around between pours and still possess the concrete 'bond'. I understand drilled bones + rebar will assist with this, but is usually right now there anything else that can extend the time.
Thoroughly clean the existing concrete and apply a product that bonds the new concrete to the old. If possible, however, remove the old and make sure there is a solid substrate for the new concrete to rest upon that has a 4 inch thick layer of cushion sand. Apr 25, 2016 - If done properly, new concrete can often be poured right over an. Or a layer of sand or stone between the new and the old concrete, the.
I furthermore understand after a few months / years this will become much even more challenging.
RLZaleski
RLZaleskiRLZaleski25933 money badges99 gold badges2020 bronze badges
1 Response
It's either a constant pour or it't not. Whether you possess to 'bond' (use rebar/scarify) is dependent on the thickness of the new pour, the present substrate and the anticipated problems it will be subjected to.
Excerpt fromBonded or Not, a conversation on sidewalk restoration making use of concrete overlays, by William G. Palmer Junior.: (concreteconstruction.internet)
Bonded overlays become part of the underlying existing pavement-they work jointly. They are 2 to 5 inches thick and are usually applied to strengthen an existing pavement or for preventive maintenance. Bonded overlays cannot end up being utilized if the existing pavement is certainly in bad condition.
Unbonded overlays, 4 to 11 inches thick depending on the desired life span and anticipated traffic, are a pavement structure on their own-the existing pavement is only used as a supporting base. This means they are usually thicker than an unbonded overlay, but are usually the just option if the pavement can be in less than good condition.
How longer you have until you must consider into accounts other considerations for concrete to self-bond; about two hrs optimum. After that, it's way beyond 'begun' to fixed. Your earlier pour should have remaining some rebar staying out, if you knew it had been heading to get multipletimespours.
The longest youcanwait around is forever (with the caveat of proper surface preparation), the longest youshouldwait is not really at all.
MazuraMazura10.6k11 platinum badge1212 magic badges4848 bronze badges